Preliminary construction activities are underway on the Rose Creek Bikeway as part of the agreement between SANDAG and Mid-Coast Transit Constructors to build this project in conjunction with the Mid-Coast Trolley. Learn more about Mid-Coast Trolley construction at KeepSanDiegoMoving.com/MidCoastNotices

Notices

Mission Bay Drive Lane Reductions: Starting the week of October 15, there will be lane reductions and traffic controls in place on southbound Mission Bay Drive, near the intersection of Damon Street. Work will occur from 11 p.m. to 5 a.m. and last approximately two weeks. Northbound and southbound Mission Bay Drive will be reduced to one lane while crews pour concrete for a portion of the bike path slab for the Rose Creek Bikeway. Flaggers will be present to help direct traffic. Please expect some noise and use extra caution when traveling near the work area. View additional information. (Posted 10/11/18)

Rose Creek Bikeway Bridge Installation - Work to Continue August 2: Due to unexpected delays, work to install a bridge for the Rose Creek Bikeway will continue on Santa Fe August 2, from 7 a.m. to 5 p.m. Motorists and cyclists can expect temporary traffic controls and delays on Santa Fe Street. Flaggers will be present, and one lane of traffic will remain open for the duration of the work. Thank you for your patience, and please use caution when traveling near construction zones. Update: Work to Continue August 6: Due to unexpected delays, work to install a bridge for the Rose Creek Bikeway will continue on Santa Fe August 6, from 6 a.m. to 5 p.m. (Posted 8/1/18; updated 8/6/18)


Rose Creek Bikeway Bridge Installation: On Tuesday, July 31, and Wednesday, August 1, construction crews will install a bridge for the Rose Creek Bikeway near Santa Fe Street, from 7 a.m. to 5 p.m. each day. To accommodate this work, motorists and cyclists can expect temporary traffic controls and delays on Santa Fe Street. Flaggers will be present, and one lane of traffic will remain open for the duration of the work. Please use caution when traveling near construction zones. View a visual simulation of the new bridge. (Posted 7/27/18)


Rose Creek Bikeway Construction to Start this Winter (Posted 12/22/17)

Preliminary construction of the Rose Creek Bikeway is scheduled to begin in January 2018. Initial work will include clearing and removing vegetation in the construction area near the creek between Santa Fe Street and I-5. Major construction, which will begin in June 2018, will include construction of the trail, under-crossings and a bridge. Project completion is anticipated in spring 2020. View additional information. 

Construction Staging Near Santa Fe Street and Damon Avenue Starts Fall 2017 (Posted 8/30/17)

Final Mitigated Negative Declaration

SANDAG, as lead agency under the California Environmental Quality Act (CEQA), has prepared a Final Mitigated Negative Declaration (MND) for the Rose Creek Bikeway project. The Draft MND was available for a 30-day public review from December 15, 2015 to January 14, 2016. After completion of the public review period, modifications were made to the Draft MND and it was recirculated for an additional 30-day public review from April 7, 2016 to May 9, 2016. The Final MND and Mitigation and Monitoring Reporting Program (MMRP) for the Rose Creek Bikeway were adopted by the SANDAG Board of Directors on May 27, 2016.

Final Mitigated Negative Declaration
Appendix A - Visual Impact Assessment
Appendix B - Air Quality Greenhouse Gas Analysis
Appendix C - Natural Environment Study
Appendix D.1 - Historic Property Survey Report and Archaeological Survey Report
Appendix D.2 - Supplemental Historic Property Survey Report for the Damon Avenue Staging Area
Appendix E - Phase I Environmental Site Assessment
Appendix F - Aerial Deposited Lead Study
Appendix G - Water Quality Technical Report
Appendix H - Preliminary Hydrology Analysis
Appendix I - Location Hydraulic Study
Appendix J - Mitigation Monitoring and Reporting Program
Appendix K - Responses to Comments

Study Reports

Coastal Rail Trail Project Study Report, October 2000 (Posted 5/20/14)

Coastal Rail Trail Project Study Report Alignment Concept Plan for Cities of Oceanside, Carlsbad, Encinitas, Solana Beach, Del Mar, and San Diego (Posted 5/20/14)

Please note that some of these files are large and may require additional time to download.

Notices about this project will be posted here as soon as they become available or sign up to be added to our email list.

Contact

Chris Carterette, AICP
SANDAG Project Manager
401 B Street, Suite 800, San Diego, CA 92101
(619) 699-7319

sandag
Regional Bikeways Project Home