1. When will construction start, and how long will it take to complete the widening all the
way to Interstate 15?

To speed construction, the corridor is being broken into smaller construction segments. The first construction project should begin in 2010 and all construction should be complete by 2014.

2. When will the environmental document be completed?

The Final Environmental Document for the Middle Segment was signed on Nov. 26, 2008. The Draft Environmental Document for the East Segment is scheduled for release in Spring 2010.

3. Will construction work be done at night?

It is very likely that work will be performed in certain areas at night to minimize construction impacts on the traveling public.