Construction of Build NCC, the first package of projects being constructed as part of the 40-year North Coast Corridor (NCC) Program, began in late 2016 and will continue through 2021. Below is a detailed list of each project’s schedule and budget. Build NCC is estimated to cost approximately $700 million with funding available from a combination of federal, state, and regional Transnet revenue sources.

Highway Projects

Schedule:

 

San Elijo Lagoon Highway Bridge Replacement

Construction Completion: 2021

 

Manchester Ave. Multi-Use Facility

Construction Completion: 2021

 

Devonshire Dr. Privacy Wall

Construction Completion: 2019

 

Encinitas and Carlsbad Sound Walls

Construction Begins: 2022

 

One HOV/carpool lane in each direction from Manchester Ave. to Palomar Airport Rd.

Construction Completion: 2021

 

One HOV/carpool lane in each direction from Palomar Airport Rd. to State Route 78

Construction Begins: 2020

 

 

Budget:

$846 million

Rail Projects

Schedule:

San Elijo Lagoon Double Track Project

Status: Under construction from late 2016 - 2018

 

Chesterfield Drive Rail Crossing Improvement Project

Status: Under construction from 2017 - 2018

 

Batiquitos Lagoon Double Track Project

Status: Under construction from late 2017 - 2019

           

Budget:

$102 million

Bike, Pedestrian and Community Enhancements Projects

Schedule:

San Elijo Lagoon Highway Bike/Ped Suspension Bridge

Status: Under construction from late 2016 - 2021

 

Manchester Ave. to Birmingham Dr. Bike Connection

Status: Under construction from late 2016 - 2021

 

Manchester Ave. Roundabout

Status: Under construction from late 2016 - 2021

 

San Elijo Lagoon Rail Pedestrian Undercrossing

Status: Under construction from late 2016 - 2018

 

Chesterfield Drive Rail Crossing Improvement Project

Status: Under construction from 2017 - 2018

 

Class 1 Manchester Ave. Bike Path

Status: Under construction from late 2016 - 2021

 

Santa Fe Dr. Interchange Bike/Pedestrian Upgrades

Status: Under construction from late 2016 - 2018

 

Encinitas Blvd. Interchange Bike/Pedestrian Upgrades

Status: Under construction from late 2016 - 2018

 

Batiquitos Lagoon Highway Bike/Ped Suspension Bridge

Status: Under construction from late 2017 - 2021

Budget:

$40 million

Environmental Enhancements Projects

Schedule:

San Elijo Lagoon Restoration

Construction Completion: 2021

Budget:

$80 million