CEQA Exemption Approved for Barrio Logan Segment

The SANDAG Transportation Committee approved the California Environmental Quality Act (CEQA) exemption for this segment on April 21, 2017. The preferred alignment study was completed in 2015. The project is currently in the final design phase and staff is working to obtain required permits for the project, including approval under the National Environmental Policy Act. Construction is expected to begin in spring 2019. 

View a map of the proposed alignment and simulations of how the project might look.

Final Mitigated Negative Declaration for Segment 8B

SANDAG, as lead agency under the California Environmental Quality Act, prepared a Final Mitigated Negative Declaration (MND) for Segment 8B of the Bayshore Bikeway. The Draft MND was available for a 30-day public review from July 27, 2016 to August 26, 2016. The Final MND and Mitigation and Monitoring Reporting Program for Segment 8B of the Bayshore Bikeway was adopted by the SANDAG Board of Directors on November 18, 2016.

Bayshore Bikeway Segment 8B Final Mitigated Negative Declaration

Appendix A – Air Quality/Greenhouse Gas Memo

Appendix B – Natural Environment Study

Appendix C – Jurisdictional Delineation Report

Appendix D – Cultural Studies

Appendix E – Phase 1 Environmental Site Assessment

Appendix F – Water Quality Assessment Report

Appendix G – Mitigation Monitoring and Reporting Program

Appendix H – Responses to Comments

Prior Notices for Segments 4B and 5 in National City

Construction of Segments 4B and 5 of the Bayshore Bikeway in National City was completed in early 2018; a ribbon cutting celebration was held on February 17, 2018. View the event invitation.

Prior construction notices included:

Construction update email (March 2017): English 

Construction notification letter (December 2016): English | Español

Project Manager

Stephan Vance
Senior Regional Planner
(619) 699-1924
Regional Bikeways Project Home